As the beach nourishment project ramps up, the County will need any late easements in hand 5 days before the contractor reaches a property in order to have enough time to add it in.
The schedule below shows the minimum date Pinellas County needs the wet copy of the easement in hand. These dates are approximate and not a guarantee of allowing the property into the project as they may reach the property faster.
Project details can be found at 2025 Pinellas County Beach Nourishment Project - Pinellas County. Aquisition Map can be found at Easements.
Text PCBEACHES to 888777 to receive latest project updates.
| Easement # | Final Date (not guaranteed)
|
| SK-265 | 9/14/2025 |
| SK-267 | 9/14/2025 |
| SK-268 | 9/14/2025 |
| SK-270 | 9/14/2025 |
| SK-277 | 9/13/2025 |
| SK-281 | 9/12/2025 |
| SK-282 | 9/12/2025 |
| SK-287 | 9/12/2025 |
| SK-300 | 8/26/2025 |
| SK-319 | 9/4/2025 |
| SK-325 | 9/6/2025 |
| SK-327 | 9/6/2025 |
| SK-328 | 9/6/2025 |
| SK-329 | 9/7/2025 |
SK-333
| 9/7/2025
|
| SK-334 | 9/7/2025 |